California Energy Commission (CEC)

ENERGY INNOVATIONS SMALL GRANT (EISG) PROGRAM

 

 

 

Project Status

High Speed Light Activated On/Off Thyristor

Dr. David Giorgi

99-17

 

 

99-17 Project Completed on 01/05/2001

 

 

·                            Completed with a 2 month extension

·                            Completed within budget

·                            Final Report has been submitted

·                            Feasibility Analysis Report has been drafted

·                            Review of Feasibility Analysis Report in process.

 

Index Page  EISG Program Page