Energy Shaver Project

James Lester

99-16

 

99-16 Project Completed on 09/13/2000

 

 

·                        Completed with a 2 month extension

·                        Completed within budget

·                        Final Report completed (see links below)

·                        Feasibility Analysis Report completed (see links below)

 

Feasibility Analysis Report (FAR)                    (Adobe Acrobat file, 6 pages, 71 kilobytes)

         Final Report (Appendix A to the FAR)      (Adobe Acrobat file, 51 pages 1,299 kilobytes)

                     Addendum to Final Report          (Adobe Acrobat file, 5 pages 113 kilobytes)

 

 

 

Self reported Follow on Funding.

Year

Source

Amount

2000

Utility

$110,000

2001

Partner

$72,500

2002

Partner

$72,500

 

 

 