Modeling
Greenhouse Temperature for Energy Efficient Production
J.H. Lieth
99-08
99-08 Project Completed on 02/26/2001
|
·
Completed on Schedule ·
Completed within budget ·
Final Report completed ·
Feasibility Analysis Report completed (see links below) Feasibility Analysis Report
(FAR) (Adobe
Acrobat file, 9 pages, 66 kilobytes) Final Report
(Appendix A to the FAR) (Adobe
Acrobat file, 32 pages 706 kilobytes) Final Report
(Appendix B to the FAR) (Adobe
Acrobat file, 1 pages 1 kilobyte) |