California
Energy Commission (CEC) ENERGY
INNOVATIONS SMALL GRANT (EISG) PROGRAM |
|
Project Status
Build and Test a 3
kW Prototype of a Co-Axial, Multi-Rotor Wind Turbine
Douglas Spriggs
Selsam
02-18
02-18 Project Status
as of 04/30/04
|
Primary Tasks |
Percent Complete % |
|
Build a 3 kilowatt multi-rotor, co-axial turbine |
100 % |
|
Preliminary testing |
60 % |
|
Revise prototype for long term testing |
60 % |
|
Perform long term (6 months) testing |
0 % |