California Energy Commission (CEC)

ENERGY INNOVATIONS SMALL GRANT (EISG) PROGRAM

 

 

 

Project Status

Dry Steam Scrubbing for Impurity Removal from Geothermal Steam

Paul Hirtz

02-13

 

 

02-13 Project Status as of 04/30/04

 

Primary Tasks

Percent Complete %

Engineering design for pilot plant upgrades

100 %

Fabricate equipment for pilot plant upgrades

100%

Install equipment for pilot plant upgrades

100 %

 Start-up and operate pilot plant facility

75 %

Evaluate initial data, design optimum bed configuration

50 %

 

 

 