INNOVATIONS SMALL GRANT (EISG) PROGRAM |
|
Project Status
Real Time Energy
Meter Radio Frequency Communications System
Elsmore William
Bush
01-11
01-11 Project Status
as of 04/30/04
|
Primary Tasks |
Percent complete |
|
Printed Circuit board Layout and Fabrication |
100% |
|
Order and Receive parts |
100% |
|
Assemble a Meter and Bench test the unit |
90% |
|
Check Output Power and Receiver Sensitivity |
90% |
|
Modify Meter Firmware |
50% |
|
Modify Base Station Software |
50% |
|
Field Testing |
12% |