Counter Rotating
Wind Turbine System
Kari Appa
00-09
00-09 Project Completed on 04/17/2002
|
·
Schedule Extended 3 months to complete ·
Completed within budget ·
Final Report completed (see links below) ·
Feasibility Analysis Report completed (see links below) Feasibility Analysis Report
(FAR) (Adobe Acrobat file,
11 pages, 71 kilobytes) Final Report
(Appendix A to the FAR) (Adobe
Acrobat file, 44 pages 1.5 MB) |
|
Self reported Follow on Funding. |
||
|
Year |
Source |
Amount |
|
2003 |
Partner |
$20,000 |